Cedar Lake Sewer Project Progress Report - July 17, 2014

The following information was collected at the project status meeting on July 17, 2014:

After mainline work in these areas are completed, it is estimated 2-3 weeks thereafter to complete paving (if applicable) and for residents to receive notices to hookup in their respective areas.

The following information is in addition to that discussed at the project status meeting.

Based on earlier schedule estimates, the contractor has deviated from the milestones projected in mid-June. They had projected to be substantially complete by July 12th and obviously this date has already passed. The latest estimate for substantial completion is mid-September. Here are some details on the delays: